UPDATE: I-91 Rockingham bridge construction

The Vermont Agency of Transportation has begun replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of Dec. 25, 2017.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!

Northbound bridge activities:

Monday & Tuesday: No work due to the Christmas holiday.
Wednesday thru Friday – Daytime:
• Continue work on Pier 1 footing.
• Continue Pier 3 excavation
• Complete driving pile in Pier 2
• Continue welding pile points for abutment 2
• Limited truck traffic on Golden Hill Road

Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084

Print Friendly, PDF & Email

Filed Under: Latest News

About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.

RSSComments (0)

Trackback URL

Comments are closed.

Never Miss a Story

Get your Wednesday Telegraph News Alert by email.
It's Free and Easy.

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Chester Telegraph will use the information you provide on this form to be in touch with you and to provide updates and marketing.