UPDATE: I-91 Rockingham Bridge construction

© 2018 Telegraph Publishing, LLC

The Vermont Agency of Transportation is replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of March 12, 2018.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!

Northbound bridge activities:

Monday thru Friday – Daytime:

• Continue work on preparation to cap Pier 1
• Continue work on Pier 2 shaft – prep for tier 4
• Continue work on Pier 3 – place tier 1; Prep for tier 2
• Continue work on I-91 Abutment 2
• Limited truck traffic on Golden Hill Road

Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084

Print Friendly, PDF & Email

Filed Under: Latest News

About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.

RSSComments (0)

Trackback URL

Comments are closed.

Never Miss a Story

Get your Wednesday Telegraph News Alert by email.
It's Free and Easy.

You have successfully subscribed to the newsletter

There was an error while trying to send your request. Please try again.

The Chester Telegraph will use the information you provide on this form to be in touch with you and to provide updates and marketing.