Schedule for Weston bridge closing

© 2016 Telegraph Publishing, LLC

Road-ClosedVTrans will shortly begin replacing bridge 98 in Weston which is located on Vermont Route 100 about a mile south of the intersection of Routes 155 and 100. Work is expected to begin on May 17 with alternating one lane traffic 24 hours a day.

The Telegraph has reported on this and several other projects which will cause delays and detours in the area this summer. Click on the links to read the stories:

Vtrans outlines Weston bridge replacement, Rt. 100 closure timeline.

Road work to impact driving around Andover, Londonderry, Weston this summer

The bridge will be closed for an estimated 21 days, starting at 6 a.m. on Friday, June 3.  

Project schedule:
May 17 to June 2 – Alternating one-way traffic 24 hours a day
(controlled by flaggers with traffic lights at night)
May 28-30 – Two-way traffic over Memorial Day Weekend
June 3- June 23 –  Bridge will be CLOSED starting at 6 a.m. on June 3
June 24 to July 8 – Alternating one-way traffic from  6 a.m. to 9 p.m. only
July 2-4: – Two-way traffic on July 4 weekend
July 10: – New bridge open to two-way traffic

Print Friendly, PDF & Email

Filed Under: AndoverLatest NewsWeston

About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.

RSSComments (0)

Trackback URL

Comments are closed.