UPDATE: I-91 Rockingham Bridge construction
Press release | Feb 04, 2018 | Comments 0
© 2018 Telegraph Publishing, LLC
The Vermont Agency of Transportation has begun replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of Feb. 5, 2018.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!
Northbound bridge activities:
Monday thru Friday – Daytime:
• Continue work on Pier 1 shaft to include placement of the upper shaft
• Continue work on Pier 2 shaft to include placement of the first shaft
• Continue pile driving at Pier 3
• Continue pile driving at Abutment 2
• Continue demolition of existing Abutment 1
• Limited truck traffic on Golden Hill Road
Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084
Filed Under: Latest News
About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.
Comments (0)
Leave a Reply
Editor's Note: Due to the recent repeated comments from some readers, including those using aliases, which is against our stated policy, we will be closing comments after an article has been up for eight days. We will allow one comment per reader per article. As always, first name or initial and last name required. COMMENTS WILL BE DELETED WITHOUT THEM. Again, no aliases accepted.