UPDATE: I-91 Rockingham bridge construction

© 2018 Telegraph Publishing, LLC

The Vermont Agency of Transportation is replacing the bridges on I-91 over the Williams River in Rockingham. The projected completion date is May 18, 2020. Here is the anticipated construction schedule for the week of Feb. 26, 2018.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! PLEASE USE CAUTION!

Northbound bridge activities:

Monday thru Friday – Daytime:

• Continue work on Pier 1 cap
• Continue work on Pier 2 and backfill footing
• Continue work on Pier 3 to include concrete pour
• Continue work on I-91 Abutment 1
• Limited truck traffic on Golden Hill Road

Find updates/changes at: http://countonitinc.com/rockingham-vt-bridges-91/
Follow us on Facebook: https://www.facebook.com/Rockingham-Bridges-595422213984445/
Follow us on Twitter: https://twitter.com/roadconstructvt #91rockbridges
Live Traffic Cameras: http://asti-traffic.com/tcm/default.aspx?id=c2a64a32-8015-48de-b622-122dd0bd7084

Print Friendly, PDF & Email

Filed Under: Latest News

About the Author: This item was edited from one or more press releases submitted to The Chester Telegraph.

RSSComments (0)

Trackback URL

Comments are closed.